Average public subsidy per data-center job in Illinois. No state reports both jobs promised and jobs actually created.27
The deal
Run the numbers
before the vote.
Every row below pairs what has been said publicly with what the record establishes. The right-hand column is never a counter-claim. It is a sourced fact or a named gap.

The ledger
What was said. What is known.
At least 50 permanent jobs.
Developer websiteOver $1 billion in taxable investment.
Developer website$75 million in projected net annual tax revenue.
Project briefing$10 million for the county through a community foundation.
Developer statementsNo impact on existing ratepayers.
Company, utility, and Commission chairman statementsThe chairman said in April that the power bill will not go up. The contract and cost-allocation study that would demonstrate this are not public. The Alabama PSC opened Docket 33709 on July 7, 2026 to review large-load contracts. In Virginia, reporting attributed an added $11.24 per month in 2026 to data-center load; in Ohio, roughly $16 per month.1112131415
Closed-loop cooling, water use like a small office building.
Developer websiteIt will be quiet and low-traffic.
Company interview, paraphrasedThe company estimates under 60 decibels at the property line. A Lowndesboro resident with three decades of data-center experience warned commissioners of continuous fan noise known as acoustic roar. Residents near comparable facilities elsewhere have reported sleep disturbance, headaches, and hypertension, and sustained sound above 65 decibels is associated with elevated stress. No noise study for this site has been published.18192021
The abatement
Thirty years is longer than it sounds.
The abatement at issue is thirty years8. At the May 26, 2026 Commission meeting the Chairman stated three times that he would not vote for a thirty-year data-center abatement, and volunteered the comparison to the forty-year abatement at the Burkville plant a mile away2223.
HB399 caps these abatements at twenty years for any abatement granted on or after January 1, 202724. A longer term, to a maximum of thirty years, survives only through a binding written agreement approved by the Department of Revenue, the Department of Commerce, and the affected local governing body, which here means this county's own Commission25.
Read the two dates together and the deadline is the whole story. A thirty-year abatement granted before January 1, 2027 is not capped. The same abatement granted after it is capped at twenty, and the county itself would have to sign off on going beyond that.
The dollar value of the abatement has never been disclosed7. That is the single number a county needs in order to decide, and it is the one number nobody has published.
And hold the abatement in proportion. As of July 24, 2026, no abatement request had been filed, no operator had been named, and the project had not been withdrawn26. The project has moved for months without asking for the one thing this section describes. A commitment about the abatement is not a commitment about the project; the water contract, the power contract, and the permits are decided elsewhere.
National context
What this asset class costs elsewhere.
Probability that projected regional demand growth across Alabama, Georgia, and the Carolinas materializes as forecast, per analysis of a December 2025 report.28
Ohio data-center demand requests after the state adopted protective ratemaking rules. How the rules are written changes how much power is actually asked for.15
U.S. data-center project value blocked or delayed by community opposition, across nearly 200 active groups in more than 24 states.29
These are national and out-of-state figures. They are context for the kind of deal being proposed, not measurements of this project. The measurements of this project have not been released.
Sources on this page
- ↑
Project Red Clay, Cloverleaf Infrastructure (2026-07-10). Developer website — view source
DisputedAccessed 2026-07-10 - ↑
Cloverleaf responds to Lowndes County data center concerns, WSFA 12 (2026-06-04). WSFA interview — view source
DisputedAccessed 2026-07-12 - ↑
Letter to the editor, The Lowndes Signal (2026-04-30). Letter to the editor, late April 2026
ReportedAccessed 2026-07-12 - ↑
Project Red Clay, Cloverleaf Infrastructure (2026-07-10). Developer website — view source
DisputedAccessed 2026-07-10 - ↑
Stakeholders consider potential data center project, The Lowndes Signal (2026-05-26). Commission meeting — view source
DisputedAccessed 2026-07-12 - ↑
Stakeholders consider potential data center project, The Lowndes Signal (2026-05-26). Project briefing — view source
DisputedAccessed 2026-07-27 - ↑
Vault open-question register, Master Evidence Dossier (2026-07-12). Open questions
Not disclosed by the projectAccessed 2026-07-12 - ↑
Stakeholders consider potential data center project, The Lowndes Signal (2026-05-26). Commission meeting — view source
ReportedAccessed 2026-07-12 - ↑
Cloverleaf emphasizes data center benefits amid community concerns, The Lowndes Signal (2026-06-01). Developer statements — view source
ReportedAccessed 2026-07-12 - ↑
Central Alabama Community Foundation, IRS Form 990 (EIN 63-0842355), ProPublica Nonprofit Explorer (2026-01-01). Nonprofit Explorer — view source
Accessed 2026-07-27 - ↑
Stakeholders consider potential data center project, The Lowndes Signal (2026-05-26). Utility statement — view source
ReportedAccessed 2026-07-27 - ↑
Mystery data center could receive 30-year tax break beside sacred Selma march ground, Yellowhammer News (2026-07-24). Reporting by Sherri Blevins, quoting an April statement — view source
ReportedAccessed 2026-07-27 - ↑
Docket 33709 public comment and reply information, Alabama Public Service Commission (2026-07-07). Generic proceeding — view source
Accessed 2026-07-12 - ↑
Virginia regulators approve new Dominion rates, Inside Climate News (2026-01-07). Rate class approval — view source
Accessed 2026-07-27 - ↑
Data Center Power Demands Are Contributing to Higher Energy Bills, Environmental and Energy Study Institute (2026-01-01). Ratemaking and demand — view source
Accessed 2026-07-27 - ↑
Cloverleaf responds to Lowndes County data center concerns, WSFA 12 (2026-06-04). Cloverleaf statement to ICN and WSFA — view source
ReportedAccessed 2026-07-12 - ↑
Vault open-question register, Master Evidence Dossier (2026-07-12). Open questions
Not disclosed by the projectAccessed 2026-07-12 - ↑
Cloverleaf emphasizes data center benefits amid community concerns, The Lowndes Signal (2026-06-01). Company interview — view source
ReportedAccessed 2026-07-27 - ↑
Cloverleaf responds to Lowndes County data center concerns, WSFA 12 (2026-06-04). Aaron Bilyeu statements — view source
ReportedAccessed 2026-07-27 - ↑
Mystery data center could receive 30-year tax break beside sacred Selma march ground, Yellowhammer News (2026-07-24). Reporting by Sherri Blevins — view source
ReportedAccessed 2026-07-27 - ↑
Living in Hell: Data Center Neighbors Grapple With Noise, Air Pollution, U.S. News & World Report (2026-04-28). Resident reporting, with EESI on the decibel threshold — view source
Accessed 2026-07-27 - ↑
Lowndes County Commission regular public meeting, May 26, 2026, Lowndes County Commission (streamed public recording) (2026-05-26). Approx. 01:40-01:58 of the public recording
Accessed 2026-07-27 - ↑
EPA enforcement record and facility listings, Burkville, U.S. Environmental Protection Agency (2012-01-01). ECHO facility record and 2012 settlement
Accessed 2026-07-27 - ↑
HB399 Enrolled, Alabama Legislature (2026-04-09). Enrolled text, Sec. 40-9B-3(12) and Sec. 3; sponsor Rep. Leigh Hulsey (R-Helena) — view source
ReportedAccessed 2026-07-27 - ↑
Alabama Senate sends bill to limit data center tax breaks to Governor, Alabama Reporter (2026-04-10). Legislative action — view source
ReportedAccessed 2026-07-27 - ↑
Mystery data center could receive 30-year tax break beside sacred Selma march ground, Yellowhammer News (2026-07-24). Reporting by Sherri Blevins — view source
ReportedAccessed 2026-07-27 - ↑
Cloudy Data, Costly Deals: How Poorly States Disclose Data Center Subsidies, Good Jobs First (2026-01-01). National subsidy review — view source
Accessed 2026-07-27 - ↑
Experts say data center growth is speculative, Southern Environmental Law Center (2025-12-01). Greenlink analysis — view source
ReportedAccessed 2026-07-27 - ↑
Data Center Watch report, Data Center Watch (2026-01-01). National registry — view source
ReportedAccessed 2026-07-27