The same developer, in other places

This has happened
somewhere before.

Lowndes County is not the first community to be asked this question. The developer has a published model and a record in several states. That record does not predict what happens here, but it does tell you what to ask.

How the business works

Land, then power, then a buyer.

This is not an accusation. It is the company's own description of what it does, and understanding it answers a question that comes up at every meeting: why nobody will say who the tenant is.

Cloverleaf co-founder Brian Janous previously led energy strategy at Microsoft before starting the company.1

  1. 01

    Assemble the land

    Cloverleaf describes itself as a developer of clean-powered, ready-to-build sites. It acquires the parcels and puts the package together before an operator is named.2

  2. 02

    Secure the power

    Power is the scarce input, not land. The company is pursuing 10 to 15 gigawatts of peak capacity across all of its sites, which makes any single county one node in a much larger pipeline.3

  3. 03

    Sell the assembled package

    The finished site is sold to a hyperscale operator. This is why the company at the county meeting is usually not the company that ends up running the building, and why the tenant question stays open.24

The record, at a glance

12 places, six states.
8 said no, paused, or stalled.

Every tile is a place where this developer's model has been proposed, sold, or is still pending, with the outcome on the public record as of late July 2026.3 advanced. One is undecided, and it is the one you live in.

Wisconsin
  • GreenleafWithdrawnJan 20265
  • Manitowoc County18-month moratoriumApr 20266
  • WrightstownOne-year moratoriumJul 20267
  • Port WashingtonAssembled and soldMay 20258
Michigan
  • DundeeDroppedOct 20259
  • Frenchtown Twp.Six-month moratoriumApr 202610
Illinois
  • TroySite rejected, 30 MW capMar 202611
  • EdwardsvilleStalled, no formal filingMar 202612
Oklahoma
  • PiedmontRezoning tabledJun 202613
Georgia
  • Columbia CountyApproved with conditionsFeb 202614
  • Monroe CountyAdvancing, expansion approvedSep 202515
Alabama
  • Lowndes CountyProposed. Undecided.Now
  • Said no, paused, or stalled
  • Sold or approved
  • Undecided

Where communities declined

Six places said no, paused, or blocked. Here is each one.

The company has written its own standard for this: it "will not work in communities where this type of development is unwelcome"16. Here is what that looked like when it was tested.

The company withdrew after talking to local leadership.

In January 2026 Cloverleaf’s Chief Development Officer stated: "After speaking to leadership at the Village of Greenleaf and the Town of Wrightstown, Cloverleaf will not be pursuing datacenters."

This matters more than any argument we could make. It is the company demonstrating, in its own words, that a community position can end a project.5

A council vote on water ended it.

Cloverleaf dropped its initial plans for a Michigan data center in October 2025 after the Dundee council voted to block the water supply. The company acknowledged it "should have done more public communication and listening."

The lever was an ordinary local utility decision, taken by an ordinary local body.9

The site was rejected. Then the rules changed.

Cloverleaf revealed concept sites in January 2026. Within a month, city officials rejected the company’s preferred site after resident opposition, and hundreds packed a public information meeting at Triad High School.

The council then approved a six-month moratorium, 6 to 0. By June, officials said the rewritten ordinance would cap data centers at 30 megawatts, a ceiling no hyperscale campus fits under. No withdrawal was ever announced. None was needed.1711

The county board moved first, before a single vote on a project.

After Cloverleaf approached landowners in Mishicot, Two Rivers, and Two Creeks townships with purchase offers, the Manitowoc County Board voted unanimously on April 29, 2026 to impose an 18-month moratorium on data-center siting. The company’s Chief Development Officer responded publicly to the vote.

No rezoning was ever filed. The board acted on the approach itself.6

A code-named project met a six-month pause.

Cloverleaf proposed a roughly 200-acre campus on a former golf course beside I-75, reported in November 2025 and carried under the code name Project Cherry Blossom. The first informational meeting drew a large crowd, much of it opposed on water, energy, and noise grounds.

On April 21, 2026 the township board voted 6 to 0 for a six-month moratorium while it rewrites its zoning ordinance. The vote is recorded in the township’s own minutes.181910

The company came back. So did the community.

Cloverleaf’s Greenleaf withdrawal named the leadership it had spoken to, and public records later showed village staff next door in contact with the company that same January, months before residents were told. By May, Wrightstown was holding listening sessions, and its board put an advisory referendum on the August 11, 2026 ballot that names no project and no company.

Residents did not wait for the ballot. After a petition gathered more than 300 signatures, trustees unanimously adopted a one-year moratorium in early July 2026. On this record a withdrawal is a pause. What a community does with the pause is up to the community.20217

Where the model completed

The model, finishing.

Port Washington, WisconsinAssembled and transferred

In May 2025 Cloverleaf assembled and annexed 1,900 acres in Port Washington, then handed the package to Vantage Data Centers for an $8 billion campus.

This is the clearest documented example of the cycle completing: the developer who appeared locally was not the operator who arrived. It is the single best reason to ask, before any vote, who the end user is and what the executed agreement says.82

The wider record

Where it advances, watch how it advances.

The Rumble Technology Campus is the model running to plan: rezoned in November 2024, expanded by 328 acres in September 2025, and developed through an affiliate named Rum Creek DevCo LLC rather than under the company’s own name. On the expansion vote, one commissioner voted no and another recused.

That November, Monroe County’s commissioners unanimously declined to sign a nondisclosure agreement with Google over the project, after their county attorney advised it would conflict with Georgia’s open-records law. A county can say yes to a project and still say no to secrecy.231524

Two more places show a mixed record. In Canadian County, Oklahoma, the Piedmont Planning Commission voted on June 1, 2026 to table Cloverleaf’s roughly 633-acre rezoning and refer it to the city council for further study. In Columbia County, Georgia, the Board of Commissioners approved Cloverleaf’s roughly 417-acre "Pumpkin Center" rezoning 4-1 on February 4, 2026, but only after imposing real conditions: buffers extended from 250 to 500 feet, berms raised from 6 to 12 feet and planted with evergreens, a 60-decibel cap at the property line, and a ban on residential development east of Highway 221. The same day, on the same agenda, that board denied a different developer’s unrelated 944-acre rezoning specifically because no end user had been identified.131425

That last fact is worth sitting with regardless of which company was involved: a lack of a named tenant has been grounds for an outright denial elsewhere. Lowndes County has that same open question.

For how each of these communities found out what was being proposed, seeThe Secrecy. For the body doing the recruiting here, seeThe LCEDC.

Sources on this page

  1. Vantage explores data center development on Cloverleaf site in Port Washington, Wisconsin, DataCenterDynamics (2025-06-11). Company background — view source

    ReportedAccessed 2026-07-28
  2. Project Red Clay / company description, Cloverleaf Infrastructure (2026-07-10). Developer website, corroborated by Yellowhammer News — view source

    ReportedAccessed 2026-07-27
  3. Investors embrace Cloverleaf’s energy-first approach to data centers, Latitude Media (2026-01-01). Company pipeline — view source

    ReportedAccessed 2026-07-27
  4. Wilson Sonsini Advises Cloverleaf on $300 Million Capital Raise, Wilson Sonsini Goodrich & Rosati (2024-07-01). Transaction announcement — view source

    Accessed 2026-07-27
  5. Cloverleaf backs out of data center project in Greenleaf, Wisconsin, DataCenterDynamics (2026-01-01). Bilyeu verbatim statement — view source

    Accessed 2026-07-27
  6. Manitowoc County Board votes unanimously to impose 18-month moratorium on data centers, WTAQ (2026-04-29). County board vote — view source

    Accessed 2026-07-28
  7. Wrightstown places moratorium on data centers, WFRV Local 5 (2026-07-07). Moratorium adoption — view source

    Accessed 2026-07-28
  8. Port Washington approves $8 billion Vantage Data Centers project, BizTimes (2025-05-01). Project approval — view source

    Accessed 2026-07-27
  9. Cloverleaf drops initial plans for Michigan data center; council votes to block water supply, DataCenterDynamics (2025-10-01). Company statement — view source

    Accessed 2026-07-27
  10. Frenchtown Charter Township Board Workshop Meeting Minutes, April 21, 2026, Frenchtown Charter Township (2026-04-21). Zoning Ordinance Amendment 300-19 — view source

    Accessed 2026-07-28
  11. Troy City Council approves six-month moratorium on data processing centers, The Troy Times Tribune (2026-03-18). Council vote coverage — view source

    ReportedAccessed 2026-07-28
  12. Metro East data center talks raise questions about residents, economic development, The Alestle, SIUE (2026-03-04). Company and city statements — view source

    Accessed 2026-07-28
  13. Piedmont planning commission tables data center decisions, calls for deeper study, KFOR (2026-06-02). Planning commission vote — view source

    Accessed 2026-07-28
  14. Columbia County Board of Commissioners approve two out of three data center projects, Byrd Farm voted down, The Augusta Press (2026-02-04). Board of Commissioners vote — view source

    Accessed 2026-07-28
  15. County approves rezoning of 328 acres on Rumble Road for tech campus expansion, WGXA (2025-09-09). Rezoning vote coverage — view source

    Accessed 2026-07-28
  16. Cloverleaf vs. Other Developments (Draft), email released under Michigan FOIA, Village of Dundee / Dundee Township, Michigan (2025-09-23). Email to Dundee officials, cc Aaron Bilyeu

    Accessed 2026-07-27
  17. Hundreds pack Troy data center meeting held by developer, as residents push back on controversial project, First Alert 4, KMOV St. Louis (2026-02-11). Public meeting coverage — view source

    Accessed 2026-07-28
  18. Cloverleaf targets 200-acre data center development in Michigan, DataCenterDynamics (2025-11-19). Proposal coverage — view source

    Accessed 2026-07-28
  19. How many AI data centers are planned in Michigan? We counted., Gander Newsroom (2026-03-02). Data center census, updated 2026-07-23 — view source

    Accessed 2026-07-28
  20. Wrightstown works with Cloverleaf on possible data center, NBC 26 (Green Bay) (2026-05-01). Email records — view source

    Accessed 2026-07-27
  21. Referendum on data centers to be held in Wrightstown, Wisconsin, DataCenterDynamics (2026-06-05). Referendum confirmation — view source

    Accessed 2026-07-28
  22. Cloverleaf reveals plans for 1,000-acre data center campus in Port Washington, Wisconsin, DataCenterDynamics (2025-01-09). Entity named from council agendas — view source

    Accessed 2026-07-28
  23. Cloverleaf seeks to expand Rumble Technology Campus in Georgia, DataCenterDynamics (2025-07-29). Expansion proposal coverage — view source

    Accessed 2026-07-28
  24. Monroe County commissioners vote no on NDA with Google on Rumble Road data center, WGXA (2025-11-18). NDA vote coverage — view source

    Accessed 2026-07-28
  25. Vault open-question register, Master Evidence Dossier (2026-07-12). Open questions

    Not disclosed by the projectAccessed 2026-07-12